| Activity |
Resp.Party |
Duration |
Sched. Start Date |
Sched. Completion Date |
1.SW masonry walls |
|
16 days |
Mon. 3/16/98 |
Mon. 4/6/98 |
| 2.SW steel erection |
|
8 days |
Fri. 5/1/98Tue. 5/26/98 |
Tue. 5/12/98?? |
| 3.SW slab on deck |
|
3 days |
Wed. 5/13/98 |
Fri. 5/15/98 |
4.SW slab on grade |
|
4 days |
Wed. 5/11/98 |
Mon. 5/18/98 |
5.SE masonry walls |
|
12 days |
Tue. 4/7/98 |
Wed. 4/22/98 |
| 6.SE steel erection |
|
6 days |
Wed. 5/13/98?? |
Wed. 5/20/98?? |
| 7.SE slab on deck |
|
2 days |
Thu. 5/21/98 |
Fri. 5/22/98 |
8.SE slab on grade |
|
3 days |
Thu. 5/12/98 |
Tue. 5/26/98 |
9.E masonry walls |
|
12 days |
Thu. 4/23/98 |
Fri. 5/8/98 |
| 10.E steel erection |
|
6 days |
Thu. 5/21/98?? |
Fri. 5/29/98?? |
11.E slab on grade |
|
3 days |
Mon. 5/11/98 |
Wed. 5/13/98 |
12.W masonry walls |
|
12 days |
Mon. 5/11/98 |
Wed. 5/27/98 |
| 13.W steel erection |
|
6 days |
Mon. 6/1/98 ?? |
Mon. 6/8/98 ?? |
14.W slab on grade |
|
3 days |
Thu. 5/28/98 |
Mon. 6/1/98 |
| 15.Wash exterior brick |
|
2 days |
Tue. 5/26/98 |
Wed. 5/27/98 |
| 16.Stain exterior concrete block |
|
7 days |
Thu. 5/28/98 |
Fri. 6/10/98 |
17.Pour electrical transformer pad |
Kelleher |
|
Wed. 5/13/98 |
Wed. 5/13/98 |
18.Pour remaining column pads betweein grids 3 & 4 to C & G.5 |
|
2 days |
Tue. 5/26/98 |
Wed. 5/27/98 |
| 19.SW install metal roof decking |
|
|
Mon. 6/1/98 |
?? |
| 20.SW Furring channels @ masonry walls |
|
|
Tue. 6/2/98 |
? |
| 21.SW roof curbs |
|
|
Wed. 6/3/98 |
Wed. 6/3/98 |
| 22.SW roofing |
|
|
Mon. 6/8/98 |
? |
| 23.SW sprinkler rough-in |
|
|
Mon. 6/15/98 |
? |
| 24.Gas service |
Minnegasco |
|
Mon. 6/1/98 |
Fri. 6/5/98 |
| 25.Fire mainFire Main Stub-in (flush witnessed by Fire Marshal) |
RSM & VS |
|
Thu. 5/14/98 |
Fri. 5/15/98 |
26.Domestic water service |
RSM |
|
Thu. 5/14/98 |
Fri. 5/15/98 |
| 27.Set interior bldg. Pad auxiliary temporary elect. Panel |
|
3 days |
Mon. 6/1/98 |
Wed. 6/3/98 |
| 28.Carmike telephone service |
|
|
|
|
| 29.West & South wall brick work |
JHM |
2 wks. |
Mon. 5/11/98 |
Fri. 5/23/98 |
| 30.Dakota Electric transformer Trench in permanent electrical service & set transformer |
Dakota Elec. |
|
Mon. 6/8/98 |
Fri. 6/12/98 |
| 31.Switch gear delivery |
|
|
Wed. 6/15/98 |
Fri. 6/19/98 |
| 32.Pre-final inspection |
|
|
|
|
| 33.Substantial completion |
|
|
|
|
| 34.Temporary Certificate of Occupancy |
|
|
|
|
| 35.Final inspection |
|
|
|
|
| 36.Final Certificate of Occupancy |
|
|
Mon. 3/3/98 |
Fri. 10/2/98 |
| 37.Move in (31 weeks following construction start on 3/5/98) |
|
31 wks |
Mon. 10/5/98 |
|