Carmike Cinemas 15-Plex
- Apple Valley, MN

Thursday, May 28, 1998

Milestone Construction Schedule

Activity Resp.Party Duration Sched. Start Date Sched. Completion Date
1.SW masonry walls   16 days Mon. 3/16/98 Mon. 4/6/98
2.SW steel erection   8 days Fri. 5/1/98Tue. 5/26/98 Tue. 5/12/98??
3.SW slab on deck   3 days Wed. 5/13/98 Fri. 5/15/98
4.SW slab on grade   4 days Wed. 5/11/98 Mon. 5/18/98
5.SE masonry walls   12 days Tue. 4/7/98 Wed. 4/22/98
6.SE steel erection   6 days Wed. 5/13/98?? Wed. 5/20/98??
7.SE slab on deck   2 days Thu. 5/21/98 Fri. 5/22/98
8.SE slab on grade   3 days Thu. 5/12/98 Tue. 5/26/98
9.E masonry walls   12 days Thu. 4/23/98 Fri. 5/8/98
10.E steel erection   6 days Thu. 5/21/98?? Fri. 5/29/98??
11.E slab on grade   3 days Mon. 5/11/98 Wed. 5/13/98
12.W masonry walls   12 days Mon. 5/11/98 Wed. 5/27/98
13.W steel erection   6 days Mon. 6/1/98 ?? Mon. 6/8/98 ??
14.W slab on grade   3 days Thu. 5/28/98 Mon. 6/1/98
15.Wash exterior brick   2 days Tue. 5/26/98 Wed. 5/27/98
16.Stain exterior concrete block   7 days Thu. 5/28/98 Fri. 6/10/98
17.Pour electrical transformer pad Kelleher   Wed. 5/13/98 Wed. 5/13/98
18.Pour remaining column pads betweein grids 3 & 4 to C & G.5   2 days Tue. 5/26/98 Wed. 5/27/98
19.SW install metal roof decking     Mon. 6/1/98 ??
20.SW Furring channels @ masonry walls     Tue. 6/2/98 ?
21.SW roof curbs     Wed. 6/3/98 Wed. 6/3/98
22.SW roofing     Mon. 6/8/98 ?
23.SW sprinkler rough-in     Mon. 6/15/98 ?
24.Gas service Minnegasco   Mon. 6/1/98 Fri. 6/5/98
25.Fire mainFire Main Stub-in (flush witnessed by Fire Marshal) RSM & VS   Thu. 5/14/98 Fri. 5/15/98
26.Domestic water service RSM   Thu. 5/14/98 Fri. 5/15/98
27.Set interior bldg. Pad auxiliary temporary elect. Panel   3 days Mon. 6/1/98 Wed. 6/3/98
28.Carmike telephone service        
29.West & South wall brick work JHM 2 wks. Mon. 5/11/98 Fri. 5/23/98
30.Dakota Electric transformer Trench in permanent electrical service & set transformer Dakota Elec.   Mon. 6/8/98 Fri. 6/12/98
31.Switch gear delivery     Wed. 6/15/98 Fri. 6/19/98
32.Pre-final inspection        
33.Substantial completion        
34.Temporary Certificate of Occupancy        
35.Final inspection        
36.Final Certificate of Occupancy     Mon. 3/3/98 Fri. 10/2/98
37.Move in (31 weeks following construction start on 3/5/98)   31 wks Mon. 10/5/98  

Project Scope   Progress Photos
Project Schedule   Project Reports
Project Contact List   Live Video Brodcasting
Project Coordination Meeting Minutes   Progress Video