| RFI No. |
DESCRIPTION |
DATE FAXED to ADG |
REQUESTED RESPONSE DATE |
DATE RESPONSE RECEIVED |
REMARKS |
| 1. |
Slab on grade vapor barrier |
3/2/98 |
3/3/98 |
3/3/98 |
Directed to install vapor barrier under stone base by structural engineer |
| 2. |
Exterior wall door frame heads |
3/3/98 |
3/4/98 |
3/4/98 |
Directed to change all exterior 2" door frame heads to 4" heads. |
| 3. |
Concrete footing re-bar location |
3/3/98 |
3/4/98 |
3/4/98 |
These are un-reinforced foundations--this is temperature steel only. |
| 4. |
Auditorium stadium seating, pad elevations |
3/6/98 |
3/11/98 |
N/A |
Resolved. See RFI No. 21 |
| 5. |
Backing and blocking drawings and details for owner provided furnishings, equipment, etc. |
3/6/98 |
3/11/98 |
|
|
| 6. |
Fire rated ceiling |
3/6/98 |
3/9/98 |
3/13/98 |
Received verbal response from script to look at sheet no. A1.2F |
| 7. |
Grade beam at grid line A |
3/16/98 |
3/16/98 |
3/16/98 |
See sketch A faxed on 3/16/98 |
| 8. |
Peer footing pad locations at grids 6 & 8 along grid A |
3/16/98 |
3/16/98 |
3/16/98 |
Extend footings 8" beyond masonry on all sides |
| 9. |
Furring channel plywood thickness required on detail 20, sheet A 6.4B |
3/16/98 |
3/20/98 |
5/6/98 |
7/8" or 1 1/4" furring channel is acceptable. |
| 10. |
Auditorium sconce shop drawing Info |
3/16/98 |
3/20/98 |
|
|
| 11. |
Locations and elevations of 2 each water proofed J boxes at building rear wall |
3/19/98 |
3/19/98 |
|
|
| 12. |
RTU’s 7 through 10 sheet M 1.3 duct dimensions |
3/20/98 |
3/24/98 |
3/26/98 |
See fax from Tom Marsh |
| 13. |
Hourly fire ratings for ceiling types 4 RB, TM2/TFR, and 4FR |
3/20/98 |
3/24/98 |
3/24/98 |
See plan sheet A1-2F & specification section 09511-1 paragraph 2.01 |
| 14. |
Slab on grade vapor barrier per letter from Terracon dated 3/13/98 |
3/23/98 |
3/25/98 |
N/A |
Poly barrier will be installed as specified directly below concrete per plan sheet S1-1 |
| 15. |
Electrical service location |
3/23/98 |
3/25/98 |
4/27/98 |
Addressed in Change Request No. 3 |
| 16. |
Tivoli Lighting |
3/23/98 |
3/25/98 |
4/27/98 |
See note No. 1 on sheet E1.1 See sheet E1.2 for locations See C.R. No. 3 for added carpet trim |
| 17. |
Theater conduit installation |
3/23/98 |
3/25/98 |
4/24/98 |
7/8" or 1 1/4" furring channel is acceptable |
| 18. |
Sound and speaker wiring |
3/23/98 |
3/25/98 |
4/27/98 |
Artech to provide sound system design. |
| 19. |
Welded grease duct at popcorn hoods |
3/23/98 |
3/25/98 |
5/18/98 |
See plan sheet M1-1 coordinate with other trades. |
| 20. |
New electrical service information for Dakota Electric |
3/23/98 |
3/26/98 |
4/2/98 |
See Campbell and Assoc. letter dated 4/2/98 |
| 21. |
Stadium seating support pads |
3/23/98 |
3/26/98 |
3/24/98 |
Thickened slab pads can be used however Re-bar is still required. Arnell-West must submit quick bolt specification information |
| 22. |
Double joist bearing plates per sheet S.12 |
3/24/98 |
3/25/98 |
3/24/98 |
Provide 2 plates at double joist locations |
| 23. |
Auditorium No. 1505, electrical panel at M 2 wall conditioned (sheet A 1/1) |
3/25/98 |
3/27/98 |
3/25/98 |
Interior wall insulation material is to be cut neatly around panel and conduit |
| 24. |
Auditorium No. 1505 screen location in relation to main electrical service entrance switchboard |
3/27/98 |
4/1/98 |
4/10/98 |
Provide 54" space between masonry wall and back side of projection screen assembly |
| 25. |
Neon lighting at lobby seating area |
3/31/98 |
4/3/98 |
4/24/98 |
Neon lighting is not required in this area |
| 26. |
Neon: Hot popcorn: sign |
3/31/98 |
4/3/98 |
4/24/98 |
Wiring to be run in wall cavity |
| 27. |
Missing drawings A 6.1 and A6.7D |
3/31/98 |
4/3/98 |
4/24/98 |
Change A6.1 to A7.1 Change A6.70 to A6.8A detail 20 |
| 28. |
Slab on grade elevations |
3/31/98 |
4/3/98 |
5/18/98(Partial) |
See ADG fax dated 5/18/98 showing revised ramps for auditoriums 1507, 1508 & 1509 |
| 29. |
Detail 1/54.2 & 51.2 @ grids 5-6 & 8-9; beam vs bar joist conflict |
4/21/98 |
4/22/98 |
4/22/98 |
Provide W18 x 35 beam @ this location. |
| 30. |
Delete 25 ea. Fire alarm pull stations. |
5/4/98 |
5/7/98 |
5/21/98 |
Disapproved, install per original plans. |
| 31. |
Relocate RTU’s 8 & 10 |
5/4/98 |
5/7/98 |
5/12/98 |
RTU’s can shift along bar joist line |
| 32. |
Compacter location |
5/6/98 |
5/11/98 |
|
|
| 33. |
Exit door stoop frost footings |
5/6/98 |
5/11/98 |
|
|
| 34. |
Fire smoke damper informtion |
5/13/98 |
5/15/98 |
|
|
| 35. |
Does C.R. No. 3. Sup-A3.3, detail 6/A3.3 only apply to 12" cmu walls? |
Mon. 6/1/98 |
Thu. 6/4/98 |
|
|
| 36. |
Is insulation required at wall type A2.2 |
Mon 6/1/98 |
Thu. 6/4/98 |
|
|
| 37. |
Needed Owner shop drawings. a. Baffle walls b. Projection windows c. Fire extinguisher cabinets |
Mon 6/1/98 |
Thu. 6/4/98 |
|
|
| 38. |
Confirm wood grain direction @ all columns, poster cases and concessions. |
Mon. 6/1/98 |
Thu. 6/4/98 |
|
|
| 39. |
"Fesco Board" roof insulation Substitution Request |
Mon 6/1/98 |
Thu. 6/4/98 |
|
|
| 40. |
|
|
|
|
|
| 41. |
|
|
|
|
|
| 42. |
|
|
|
|
|