Carmike Cinemas 15-Plex
- Apple Valley, MN

Response Summary

Owner: Carmike Cinema’s

Project: Carmike Cinema’s-15 Plex

Architect: Artech Design Group (ADG)

Location: Apple Valley, Minnesota

General Contractor: Arnell-West, Inc.

Date:

RFI No. DESCRIPTION DATE FAXED to ADG REQUESTED RESPONSE DATE DATE RESPONSE RECEIVED REMARKS
1. Slab on grade vapor barrier 3/2/98 3/3/98 3/3/98 Directed to install vapor barrier under stone base by structural engineer
2. Exterior wall door frame heads 3/3/98 3/4/98 3/4/98 Directed to change all exterior 2" door frame heads to 4" heads.
3. Concrete footing re-bar location 3/3/98 3/4/98 3/4/98 These are un-reinforced foundations--this is temperature steel only.
4. Auditorium stadium seating, pad elevations 3/6/98 3/11/98 N/A Resolved. See RFI No. 21
5. Backing and blocking drawings and details for owner provided furnishings, equipment, etc. 3/6/98 3/11/98    
6. Fire rated ceiling 3/6/98 3/9/98 3/13/98 Received verbal response from script to look at sheet no. A1.2F
7. Grade beam at grid line A 3/16/98 3/16/98 3/16/98 See sketch A faxed on 3/16/98
8. Peer footing pad locations at grids 6 & 8 along grid A 3/16/98 3/16/98 3/16/98 Extend footings 8" beyond masonry on all sides
9. Furring channel plywood thickness required on detail 20, sheet A 6.4B 3/16/98 3/20/98 5/6/98 7/8" or 1 1/4" furring channel is acceptable.
10. Auditorium sconce shop drawing Info 3/16/98 3/20/98    
11. Locations and elevations of 2 each water proofed J boxes at building rear wall 3/19/98 3/19/98    
12. RTU’s 7 through 10 sheet M 1.3 duct dimensions 3/20/98 3/24/98 3/26/98 See fax from Tom Marsh
13. Hourly fire ratings for ceiling types 4 RB, TM2/TFR, and 4FR 3/20/98 3/24/98 3/24/98 See plan sheet A1-2F & specification section 09511-1 paragraph 2.01
14. Slab on grade vapor barrier per letter from Terracon dated 3/13/98 3/23/98 3/25/98 N/A Poly barrier will be installed as specified directly below concrete per plan sheet S1-1
15. Electrical service location 3/23/98 3/25/98 4/27/98 Addressed in Change Request No. 3
16. Tivoli Lighting 3/23/98 3/25/98 4/27/98 See note No. 1 on sheet E1.1 See sheet E1.2 for locations See C.R. No. 3 for added carpet trim
17. Theater conduit installation 3/23/98 3/25/98 4/24/98 7/8" or 1 1/4" furring channel is acceptable
18. Sound and speaker wiring 3/23/98 3/25/98 4/27/98 Artech to provide sound system design.
19. Welded grease duct at popcorn hoods 3/23/98 3/25/98 5/18/98 See plan sheet M1-1 coordinate with other trades.
20. New electrical service information for Dakota Electric 3/23/98 3/26/98 4/2/98 See Campbell and Assoc. letter dated 4/2/98
21. Stadium seating support pads 3/23/98 3/26/98 3/24/98 Thickened slab pads can be used however Re-bar is still required. Arnell-West must submit quick bolt specification information
22. Double joist bearing plates per sheet S.12 3/24/98 3/25/98 3/24/98 Provide 2 plates at double joist locations
23. Auditorium No. 1505, electrical panel at M 2 wall conditioned (sheet A 1/1) 3/25/98 3/27/98 3/25/98 Interior wall insulation material is to be cut neatly around panel and conduit
24. Auditorium No. 1505 screen location in relation to main electrical service entrance switchboard 3/27/98 4/1/98 4/10/98 Provide 54" space between masonry wall and back side of projection screen assembly
25. Neon lighting at lobby seating area 3/31/98 4/3/98 4/24/98 Neon lighting is not required in this area
26. Neon: Hot popcorn: sign 3/31/98 4/3/98 4/24/98 Wiring to be run in wall cavity
27. Missing drawings A 6.1 and A6.7D 3/31/98 4/3/98 4/24/98 Change A6.1 to A7.1 Change A6.70 to A6.8A detail 20
28. Slab on grade elevations 3/31/98 4/3/98 5/18/98(Partial) See ADG fax dated 5/18/98 showing revised ramps for auditoriums 1507, 1508 & 1509
29. Detail 1/54.2 & 51.2 @ grids 5-6 & 8-9; beam vs bar joist conflict 4/21/98 4/22/98 4/22/98 Provide W18 x 35 beam @ this location.
30. Delete 25 ea. Fire alarm pull stations. 5/4/98 5/7/98 5/21/98 Disapproved, install per original plans.
31. Relocate RTU’s 8 & 10 5/4/98 5/7/98 5/12/98 RTU’s can shift along bar joist line
32. Compacter location 5/6/98 5/11/98    
33. Exit door stoop frost footings 5/6/98 5/11/98    
34. Fire smoke damper informtion 5/13/98 5/15/98    
35. Does C.R. No. 3. Sup-A3.3, detail 6/A3.3 only apply to 12" cmu walls? Mon. 6/1/98 Thu. 6/4/98    
36. Is insulation required at wall type A2.2 Mon 6/1/98 Thu. 6/4/98    
37. Needed Owner shop drawings. a. Baffle walls b. Projection windows c. Fire extinguisher cabinets Mon 6/1/98 Thu. 6/4/98    
38. Confirm wood grain direction @ all columns, poster cases and concessions. Mon. 6/1/98 Thu. 6/4/98    
39. "Fesco Board" roof insulation Substitution Request Mon 6/1/98 Thu. 6/4/98    
40.          
41.          
42.          



Project Scope   Progress Photos
Project Schedule   Project Reports
Project Contact List   Live Video Brodcasting
Project Coordination Meeting Minutes   Progress Video

Home | Intro | Resumé | Cost Estimating | Featured Projects | Contact Form | Doug's Page

Copyright © 1997 - Professional Project Management - All Rights Reserved.